How to Study Crashing and Fast Tracking for the PMP Certification?
Every
project manager is well aware that schedules are continuously changing. And,
sadly, plans rarely grow shorter; they tend to get longer! Alternatively, your
consumer desires an expedited delivery. And now, what appeared to be an
excellent timeline at the start of the project has devolved into a complete
mess, and you will never be able to complete it on time!
Unless,
of course, you act immediately by crashing or fast tracking.
That
is the subject of this article, which will cover all you need to know about both
strategies in preparation for the Project
Management Professional (PMP)® Exam.
Crashing and Fast Tracking Are Two Techniques for Compressing the Schedule
Schedule
compression is used to reduce the time of a project without altering its scope.
This
is advantageous if you have fallen behind the initial schedule and now need to
"catch up," or if you wish to complete the project sooner because a
competitor is developing a similar product. You want to be first to market.
Additionally, completing a project sooner than scheduled initially may be a
strategic decision depending on other factors.
You
must understand two schedule compression approaches to pass the PMP®
Exam:
Crashing
Increase the resources allocated to your project to expedite its completion. Almost invariably, there is a financial cost associated with crashing.
Fast Tracking
Perform tasks in parallel to finish them more quickly. This type of job overlap frequently increases risks.
Compression of the schedule should always be focused on the critical route of the project, as the critical path defines the project's finish date. And if you want to complete your project sooner, it makes little sense to compress operations without bearing on the project's completion date.
Do you want to know if you're ready to take the real PMP® test? Try answering this free PMP® Practice Tests to assess yourself!
What is Fast Tracking?
Fast Tracking Definition
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
PMBOK® Guide
Fast
tracking is accomplished by rescheduling various activities within the project
to be executed concurrently rather than sequentially. Whenever possible, begin
with this strategy. Why? Because there are no associated costs. Essentially,
you're "merely altering the schedule."
However,
this strategy is only applicable if activities can be overlapped effectively.
For
instance, it is possible to begin prototyping even if the design specifications
are not quite finalized. You may overlap them as long as a sufficient number of
specs have been developed to start prototyping.
Fast
tracking carries the potential of encountering issues if parallel aspects of
the project contain dependencies. In this example, the risk is that you will
need to redo the prototype if the design changes mid-process. However, if the
design remains stable, production can begin considerably sooner.
Thus,
the project manager must balance risk and opportunity.
Fast Tracking Example
You're
checking your project's schedule and discover that the project's completion
deadline has gone past the date promised. You need to re-establish the order without
incurring further costs.
A thorough study reveals three actions that might be started sooner to expedite the project's completion:
- After
integration testing is complete but before final sign-off, end-user
documentation can begin.
- If
the first three sessions can be educated using the test system, user training
sessions can begin before the final system being configured and installed.
- The
final system's configuration and installation might begin three days before
testing is completed.
Each of these suggestions will help you meet your deadline but will also increase the project's risk. As the project manager, it is your obligation to analyze the alternatives and decide which (or all) of them will be used to compress the timetable.
A Hand-Picked Article: What is a Project Management Plan, and How Do You Write One?
What is Crashing?
Crashing Definition
A technique used to shorten the schedule duration for the least incremental cost by adding resources.
PMBOK® Guide
When
using the crashing technique, any additional costs associated with accelerating
the project are weighed against the potential benefits of completing it sooner.
More factors to consider while employing the crashing strategy include increasing
project resources, providing for additional overtime, paying extra to expedite
delivery of crucial components, etc.
Crashing
works only if additional resources enable you to accomplish the project more
quickly. For example, crashing will not operate if "the concrete in the
foundation must dry for three days."
Crashing Example
You
are in charge of a project to update your organization's regulations. The new
law takes effect on June 30th, and each day your organization is delayed will
result in a government-imposed fee. You've already optimized and simplified the
project's timetable to the maximum extent possible, but additional optimization
appears impossible without drastic measures.
You and the project sponsor agree during a discussion that the primary limitation is completing the project on time. Additional funding will need to be requested.
- You
do a critical path analysis.
- You
identify all jobs that the use of additional resources could streamline.
- You
calculate the cost and number of days saved by adding additional resources for
each task.
- You
determine the least expensive course of action.
- You offer the sponsor a crash budget and an updated schedule.
Crashing vs. Fast Tracking
The
reality of project management is that you will occasionally need to compress
the project timetable to provide the product, service, or result ahead of
schedule. Schedules are constantly changing; in most situations, they become
longer rather than shorter, which can have a detrimental effect on the initial
schedule because the project team will not complete it within the allotted
time.
There
is no reason to fast track or crash any activities that are not on the critical
path—you will gain no time on your overall timetable if your critical path
cannot be shortened.
Summary
Fast
tracking entails the execution of multiple tasks concurrently, whereas crashing
entails adding resources to a project.
There
is an increased danger associated with fast tracking, but there is an increased
expense associated with crashing.
With
a better understanding of the schedule compression approaches of fast tracking
and crashing, their advantages and disadvantages, and the conditions in which
they can be used, we're confident you'll see results in no time.
Suppose you're working toward a PMP® certification — or are considering doing so. In that case, SPOTO offers the latest and accurate exam dumps and best service package, including application, recertification services that are designed to help you pass the PMP® exam on your first try.