Download 100% Latest and Real PMP Exam Questions
Are You a Certified PMP®? Take Our Free Test Immediately
Preparing
for an exam in 2021 can be stressful at times, especially when there is a lot
to learn in a short amount of time. SPOTO
PMP® exam dumps, covering real exam questions, are the ideal resource for
preparing and checking your preparation level continuously. It aids in PMP®
exam preparation online by familiarizing you with the style and scope of the
PMP® testing paper.
Here are ten up-to-date and authentic exam questions for you to practice on! Now, go ahead and give it a shot!
Related Reading:
Download Free and Up-to-Date PMP Exam Preparation Practice Test
Free PMP® Sample Questions: Test Exam Cost Controlling & Earned Value Analysis
[Updated 2021] Take Latest and Free PMP Practice Exam to Test Yourself!
Download 2021 Latest and Free PMP Practice Test to Test Yourself
QUESTION 1
An
agile project is running its fifth iteration out of eight After the last
iteration planning, the team was informed that there is a new competitor in the
market, and it is necessary to move faster to ensure market share is not
missed.
What
should the project manager do?
A. Add the competitor's functionalities to the
product backlog to improve the product.
B. Help the team to find a new approach to
launch the product as soon as possible.
C. Ask the team to increase the velocity to
launch the product as soon as possible.
D. Ask the sponsor to add more people to the
team.
Correct Answer: B
QUESTION 2
One
of a project manager's team members is continuously improving. This team member
has been a role model and mentor to others in the organization. How should the
project manager acknowledge this team member's commitment?
A. Appreciate this team member's performance
throughout the project life cycle.
B. Send this person to a meeting to negotiate
the scope with the client
C. Promote this team member to a coaching role
after this project is completed.
D. Document it in the team member's end of year
performance review.
Correct Answer: A
QUESTION 3
A
project manager has been assigned to a project and receives the project charter
from the project management office (PMO) The document is very clear about
customer requests. During Project Scope Management, some requirements seem to
be different from the ones specified within the project charter.
What
should the project manager do?
A. Explain to the sponsor that these requests
could endanger the schedule and cost of the project
B. Use a focus group and brainstorming sessions
to gather more details about the project scope.
C. Register the changes in the configuration
management plan and send it to the change control board (CCB)
D. Modify the baseline of the project for minor
impact changes to the project scope
Correct Answer: C
QUESTION 4
A
project manager is implementing a new software system. Some department staff
members are questioning the necessity of the change and feel the new system will
impede their current processes.
What
should the project manager have done at the start of the project to prevent
this resistance?
A. Encouraged leadership to discuss the change
with departments that are typically resistant to change
B. Ensured that the company culture encourages
changes before accepting the project.
C. Involved stakeholders from all levels of the
company so everyone understands the change
D. Created a communications management plan that
outlined the method of communicating to stakeholders
Correct Answer: C
Are you current on recent changes to project management practices? Take our PMP Exam Practice Test right now to find out!
Want more Free PMP Exam Practice Tests? Contact us!
QUESTION 5
During
the development of a product, the project manager observes conflicts between
project stakeholders, resulting in deliverable and output approval delays. On
which area should the project manager focus?
A. Revisiting the project management plan to
ensure deliverables are on time
B. Reviewing the business case and identifying
gaps within scope
C. Revisiting the stakeholder engagement plan,
focusing on specific overlooked stakeholders
D. Increasing the frequency of project update
meetings to keep stakeholders informed
Correct Answer: C
QUESTION 6
After
a couple of iterations, the project manager decides to present the product to a
key stakeholder. The stakeholder's feedback is that the team missed the mark on
many features.
What
should the project manager do to avoid this in the future?
A. Evaluate the team's skills to look for
someone with experience in product design and assign that person the task of
rebuilding the product interface.
B. Incorporate design thinking practices into
the project life cycle to better understand the product's personas and be more
effective to match their needs
C. Set up requirements gathering sessions with
all key stakeholders to evaluate the scope once again and reprioritize the
backlog based on the sessions.
D. Schedule adequate sprint demos to gather
early feedback from the stakeholders and adapt the plan accordingly.
Correct Answer: C
QUESTION 7
During
the execution of a project within an operations function, the project manager
encounters scope changes and a delay in the delivery of critical tasks. How
should the project manager address this situation?
A. Initiate the change request to modify the
scope and adjust the timelines.
B. Call for a team meeting to decide if the
changes should be included.
C. Communicate the concerns to the project
management office (PMO) during the weekly project reports.
D. Conduct an impact analysis and present the results
to the steering committee for approval.
Correct Answer: D
QUESTION 8
The
programming activities of a project were planned to last 35 days per module,
but the programming of the first module has taken 45 days. What should the
project manager do?
A. Ask the team to work overtime to complete the
deliverable on time.
B. Check the scope to verify if there is scope
creep and get the project on schedule.
C. Evaluate the situation and identify ways to
compress the schedule without impacting baselines.
D. Submit a change request to the project
sponsor to change the schedule.
Correct Answer: C
QUESTION 9
A
large project is affecting the neighborhood in which it is located. The
neighbors are not satisfied with the project, and their resistance to the project
may affect the project deadline.
What
two actions should the project manager take? (Choose two)
A. Ask the mayor of the city to use their
authority to stop neighborhood resistance
B. Set up a meeting with neighborhood
representatives to win their cooperation.
C. Send letters to the neighbors and ask them
kindly not to disturb the project
D. Analyze the situation and find out what is
causing the neighborhood's negative attitude.
E. Ask the customer to extend the project
deadline to allow time for conflict resolution.
Correct Answer: BD
QUESTION 10
After
gathering all the requirements for a project with dependencies on external
stakeholders, the project team is finishing the second iteration. At this
point, the project manager learns about a possible change in regulations that
would prevent the product launch.
What
should the project manager do to realize benefits?
A. Add an entry in the risk log.
B. Implement the changes.
C. Review target benefits.
D. Improve the team's velocity.
Correct Answer: A
Summary
To pass the PMP® exam in 2021, you must eliminate all concerns and properly practice with SPOTO PMP Exam Dumps before sitting for the actual exam. Through a thorough study of your performance, SPOTO PMP® exam dumps assist you in building the optimal test-taking strategy. With SPOTO PMP® practice questions, you may assess yourself at any time and from any location, boost your confidence, overcome your errors, and improve your speed and accuracy. Give your preparation an immediate boost with our PMP® exam dumps!